Granny flat build timeline: what happens week by week

Last reviewed: August 2026
By BlueGum Granny Flats
Builder Licence 247388C
HIA member
HIA GreenSmart
In-house approvals, not outsourced
NSW Fair Trading

Construction of a granny flat typically runs 12 to 16 weeks from site set-up to handover. The stages happen in a fixed order because each one depends on the last, and knowing that order tells you what you are looking at when you glance out the back window and what you need to have decided by then.

This is a typical sequence. Weather, inspections and site conditions move it around.

The full sequence

Weeks
Stage
What you will see
1 to 2
Site set-up and excavation
Fencing, machinery, earth moving, service trenching
2 to 3
Slab
Formwork, steel, plumbing rough-in, concrete pour
4 to 6
Frame and roof
The shape of the building appears, then a roof
6 to 8
Lock-up
Windows, external doors, external cladding
8 to 9
Rough-in
Electrical and plumbing inside the walls
9 to 12
Internal fit-out
Insulation, linings, cornices, cabinetry, tiling
12 to 14
Finishes
Painting, floor coverings, fixtures, fittings
14 to 16
External works and handover
Driveway, paths, landscaping, final inspections
Stage
Site set-up and excavation
What you will see
Fencing, machinery, earth moving, service trenching
Stage
Slab
What you will see
Formwork, steel, plumbing rough-in, concrete pour
Stage
Frame and roof
What you will see
The shape of the building appears, then a roof
Stage
Lock-up
What you will see
Windows, external doors, external cladding
Stage
Rough-in
What you will see
Electrical and plumbing inside the walls
Stage
Internal fit-out
What you will see
Insulation, linings, cornices, cabinetry, tiling
Stage
Finishes
What you will see
Painting, floor coverings, fixtures, fittings
Stage
External works and handover
What you will see
Driveway, paths, landscaping, final inspections

What happens at each stage

Weeks 1 to 2: site set-up and excavation

Site fencing goes up, access is established, and the ground is prepared. Excavation levels the building area, and service trenches are dug for water, sewer, power and data.

This is the stage where surprises appear. Rock, unexpected soil conditions, or a service in an unexpected position all show up now rather than later.

What you need decided: everything about siting and levels. Changing the position of the building after excavation is expensive.

Weeks 2 to 3: slab

Formwork is set out, reinforcing steel is placed, and the under-slab plumbing is installed. An inspection happens before the pour, then the concrete goes down and cures.

The slab is a hard commitment point. Plumbing positions are set in concrete, literally.

What you need decided: bathroom, kitchen and laundry layouts, because the drainage positions are fixed here.

Weeks 4 to 6: frame and roof

The frame goes up and suddenly there is a building. Roof trusses follow, then roofing.

This is the stage where people finally get a feel for the size of the rooms, and where the occasional change of heart happens. Changes here are still possible but they are no longer cheap.

What you need decided: window and door positions, which are framed now.

Weeks 6 to 8: Lock-up

Windows and external doors are installed and the external cladding goes on. Once the building can be locked, materials can be stored inside and weather stops holding things up.

Lock-up is a common progress payment stage.

Weeks 8 to 9: rough-in

Electrical cabling and plumbing pipework are run through the wall and ceiling cavities before they are closed up. Inspections happen at this point.

What you need decided: every power point, light switch, light fitting and tap position. This is the last easy moment to change them. After the walls are lined, moving a power point means cutting into plasterboard.

Weeks 9 to 12: internal fit-out

Insulation goes in, then wall and ceiling linings, then cornices and skirtings. Kitchen and bathroom cabinetry is installed and wet area tiling is done.

The building starts to look finished from the inside.

What you need decided: all finishes, because they are being installed. Tiles, cabinetry, benchtops and tapware should have been selected weeks earlier.

Weeks 12 to 14: finishes

Painting, floor coverings, and the installation of fixtures and fittings. Appliances go in. The building becomes a home rather than a shell.

Weeks 14 to 16: external works and handover

Driveway and paths, any fencing, landscaping and turf. Final plumbing and electrical connections are completed and tested.

Then final inspections, the occupation certificate, and handover.

What happens at handover: you walk through the building with your builder, note any defects, and receive the keys along with your certification and warranty documentation.

The decisions that hold everything up

Looking at the sequence, the same pattern shows up repeatedly. The stages that stall are almost always waiting on a decision rather than on work.

Decision
Must be made by
Siting and levels
Before excavation
Wet area layouts
Before slab
Window and door positions
Before frame
Electrical and tap positions
Before rough-in
Tiles, cabinetry, benchtops
Before fit-out
Paint colours and floor coverings
Before finishes
Must be made by
Before excavation
Must be made by
Before slab
Must be made by
Before frame
Must be made by
Before rough-in
Must be made by
Before fit-out
Must be made by
Before finishes

Making all of these before construction starts is the single most effective thing you can do to keep a build on schedule.

What can move the timeline

  • Weather. Mostly affects the early stages. Excavation and the slab pour need reasonably dry conditions. Once the roof is on, it matters much less.
  • Inspections. Several stages require an inspection before the next can start.
  • Rock or unexpected site conditions. Discovered during excavation.
  • Variations. Every change you request has a time cost as well as a price.
  • Material or trade availability. Outside anyone’s control, though a builder with steady trades manages it better.
Share with

Frequently asked
questions

Arrange it with your builder rather than dropping in. Active building sites have safety requirements and there are insurance implications. Most builders are happy to walk you through at agreed times.

Yes, but the cost rises sharply the later you leave it. Moving a power point before rough-in is minor. Moving it after the walls are lined and painted is not. Any variation should be documented in writing with a price before the work happens.

The early stages are affected most, particularly excavation and the slab. Once the building reaches lock-up, internal work continues regardless of weather.

Generally no. Certifier and trade inspections are arranged by your builder. You will be involved at handover.

Note them at the walkthrough. There should be a defects liability period during which they are rectified. Ask your builder how long that period is and how the process works before you sign the contract.

See the process from the inside

Every build follows this sequence, and knowing it makes the whole thing far less opaque.

Read more about our construction process, or call BlueGum on 1300 060 651.

Building granny flats since

Since 2012

Builder licence

247388C, verifiable through NSW Fair Trading

Industry body

Housing Industry Association member

MBA NSW Excellence in Housing Awards

Winner 2021, Winner 2023, Finalist 2020

Completed granny flats documented on this site

70+

Approvals

CDC and DA, both managed in-house

Pricing

Fixed price after a site assessment, 2-bedroom from $134,990

Building granny flats since

Since 2012

Builder licence

247388C, verifiable through NSW Fair Trading

Industry body

Housing Industry Association member

MBA NSW Excellence in Housing Awards

Winner 2021, Winner 2023, Finalist 2020

Completed granny flats documented on this site

70+

Approvals

CDC and DA, both managed in-house

Pricing

Fixed price after a site assessment, 2-bedroom from $134,990

BlueGum Granny Flats is a licensed NSW builder, licence number 247388C, and a member of the Housing Industry Association. Setback, frontage and landscaping figures are drawn from the State Environmental Planning Policy (Housing) 2021 as in force in August 2026 and are general information, not planning advice. Other planning instruments applying to your land can vary them. Confirm the requirements for your block with a certifier or your council. Cost ranges are drawn from published 2026 Sydney market guides and are not a quote.