On the fast approval pathway, a Sydney granny flat typically runs about 6 to 9 months from first enquiry to handover. Roughly 2 months of that is design and documentation, 1 to 2 months is approval, and 3 to 4 months is construction. On the council approval pathway, add 3 to 6 months.
The part people underestimate is not construction. It is everything that has to happen before construction can start.